Chambersburg Public Opinion - Contractors play catch... -
[Cached Version]
Published on: 7/21/2006
Last Visited: 7/21/2006
Chambersburg Area School District's building and grounds supervisor, Dick Bender, said rain is to blame for the delays, but he said he is pleased with the progress crews are making.
"We're starting to try to get back on schedule," Bender said.
...
Bender added that rain this summer has come in heavy downpours, which wreaks havoc on the site.
"We get one rain storm, and it has to be a couple of inches.The water just sits there because it has no place to go," Bender said."If we'd get a little bit of rain at a time, it would have the chance to go away and the area dry up pretty quickly."
He said heavy rains do nothing but turn the area into a mud pit that limits activity by heavy equipment.
"If we try to run some of this equipment through the mud, all we do is create big ruts that we'd have to go back in and fix," he said."We're trying not to redo the work we've already done."
Bender said crews this week are installing the fencing around the complex, painting the concession stands, finishing some
...
Bender said it is possible that the first week of practices for Chambersburg's fall sports teams, set to begin Aug. 14, will not take place on the field.But, he said officials are working with the coaching staff in an effort to "try to accommodate the teams as best we can."
He said it's possible that temporary fencing might go up around the field so teams can use the turf, but would be shielded from construction at the bleacher areas.