About | Free Trial

Last Update

2015-10-05T00:00:00.000Z

This profile was last updated on . .

Is this you? Claim your profile.

Wrong Mark Hamarich?

Mark Hamarich A. PE

Principal Project Manager

Kinder Morgan , Inc.

Direct Phone: (713) ***-****       

Email: m***@***.com

Kinder Morgan , Inc.

1001 Louisiana Street Suite 1000

Houston, Texas 77002

United States

Company Description

Kinder Morgan, Inc. (NYSE: KMI) is the largest energy infrastructure company in North America. It owns an interest in or operates approximately 84,000 miles of pipelines and 165 terminals. more

Find other employees at this company (8,083)

Background Information

Web References (6 Total References)


D Three Technology - Natural Gas Scavengers: Marcellus Shale Natural Gas Pipeline

www.dthreetechnology.blogspot.com [cached]

We re a pipeline company, said Mark Hamarich, ElPaso Corp. representative and project manager for the Tennessee Gas Pipeline. Our business is to transport natural gas. As natural gas production increases, supply-line space is at a premium, creating a need to expand capacity. Currently, ElPaso Corp., through its Tennessee Gas subsidiary, maintains a 24-inch line and is working to improve and expand the pipeline infrastructure. The 300-line project is aimed at the Northern Tier of Pennsylvania and will increase capacity by installing seven looping segments totaling 127 miles of 30-inch pipeline. The project includes installation of two additional compression stations and upgrades to existing compressor stations. We re proposing to build loop lines adjacent to the existing line, Hamarich said.

...
According to Hamarich, land-moving practices are carefully monitored to separate the top soil from the subsoil and to follow all Department of Environmental Protection erosion control and sedimentation guidelines and inspections. Agricultural land, wetlands, water bodies and streams, cemeteries are all things we deal with, said Hamarich, There s a lot of investigating that goes into this. After construction, the land is re-seeded and restored. Crop damages are paid according to the market value of the specific crop. We ll work with the farmers to make sure the crop land is brought back, Hamarich said. As long as the pipeline is in existence, the pipeline company will maintain the right of way to keep the area clear of trees that might damage the pipeline itself. If a right of way cannot be negotiated, the pipeline company is authorized to employ eminent domain to secure the necessary land rights, although this is used as a last resort. Once the pipeline is in place, the biggest challenge facing the pipeline companies is to prevent damages. Do not dig near the pipeline, Hamarich said.


The representatives from Kinder ...

www.recorder.com [cached]

The representatives from Kinder Morgan included Allen Fore, the vice president of public affairs, Mark Hamarich, the company's project manager, Land Manager Mike Lennon, and Curtis Cole, the company's director of business development.

...
When asked about the aesthetic aspects of the pipeline, Hamarich noted that the entirety of the pipeline would be buried, that only the compressor stations and valves to regulate the pipe would be visible above ground, and that it would not impede recreational activities. He also said measures would be taken to reduce noise from the compressor stations.
He also said no gas would be released from either the pipeline or the compressor stations during "regular operation."
Hamarich also spoke about the various safety measures that would be in place, including electric "cathodic" protection that would prevent the pipes from corroding, pressure tests, right-of-way length, and extra wall thickness in populated areas.


The representatives from Kinder ...

www.recorder.com [cached]

The representatives from Kinder Morgan included Allen Fore, the vice president of public affairs, Mark Hamarich, the company's project manager, Land Manager Mike Lennon, and Curtis Cole, the company's director of business development.

...
When asked about the aesthetic aspects of the pipeline, Hamarich noted that the entirety of the pipeline would be buried, that only the compressor stations and valves to regulate the pipe would be visible above ground, and that it would not impede recreational activities. He also said measures would be taken to reduce noise from the compressor stations.
He also said no gas would be released from either the pipeline or the compressor stations during "regular operation."
Hamarich also spoke about the various safety measures that would be in place, including electric "cathodic" protection that would prevent the pipes from corroding, pressure tests, right-of-way length, and extra wall thickness in populated areas.


TGP 300 Line Project > Contacts

www.kindermorgan.com [cached]

Mark Hamarich Project Manager (713) 420-6295 Mark_Hamarich@kindermorgan.com


TGP 300 Line Project > Contacts

www.elpaso.com [cached]

Mark Hamarich Project Manager (713) 420-6295 Mark.Hamarich@elpaso.com

Similar Profiles

Other People with this Name

Other people with the name Hamarich

Danielle Hamarich
Alere Inc.

Peter Hamarich
Building Service 32BJ Benefit Funds

Andrew Hamarich
Lehigh Valley Hospital

Peter Hamarich
32BJ Benefit Funds

Joseph Hamarich
DCG Partnership 1 LTD

Browse ZoomInfo's Business Contact Directory by City

Browse ZoomInfo's
Business People Directory

Browse ZoomInfo's
Advanced Company Directory