Share This Profile
Share this profile on Facebook.
Link to this profile on LinkedIn.
Tweet this profile on Twitter.
Email a link to this profile.
See other services through which you can share this profile.
This profile was last updated on 7/17/12  and contains information from public web pages.

Pre-construction Administrator

Alabama Department of Transportation
 
Background

Employment History

42 Total References
Web References
ALDOT Pre-construction Administrator ...
www.timesdaily.com, 17 July 2012 [cached]
ALDOT Pre-construction Administrator Allen Teague said some of the 12½ miles has a middle turn lane, but 70 percent of it is two two-lane roads with nothing more than a line separating oncoming traffic.
...
Teague said one of the goals of the project is to find ways to reduce the slickness of the road when it is wet. The resurfacing could help fix the problem.
"We're trying to help get some of the water off the road," he said.
...
Teague said the project is being paid for by ALDOT and no local funds are being requested. He said no rights-of-way will be required.
Allen Teague, a ...
www.timesdaily.com, 14 Aug 2011 [cached]
Allen Teague, a preconstruction engineer with the Alabama Department of Transportation, said the base and pave portion of the project is scheduled for fiscal year 2012 and will most likely be bid sometime after the first of the calendar year.
The remaining phases of the widening project are currently scheduled for fiscal year 2016, he said.
The next project stretches from Alabama 64 to Lauderdale 140. The last project runs from Lauderdale 140 to the Alabama-Tennessee state line.
Teague said in both those projects, the grade and drain and base and pave portions will be done at the same time.
Grade and drain involves building new roadbed and installing drainage pipes and ditches, while base and pave involves paving the new roadway, landscaping and traffic striping.
Teague said U.S. 43 will become an undivided five-lane road from Alabama 64 to the state line.
Teague said U.S. 43 will transition from a divided four-lane to an undivided five-lane highway just north of the Alabama 64 intersection and connect with the undivided five-lane section that runs from the Tennessee state line to Lawrenceburg.
Right of way acquisition for the next two phases is scheduled for fiscal year 2012, Teague said. The state already owns much of the right of way along U.S. 43 south of the state line.
Teague said right of way was purchased when the road was originally built, but additional right of way is needed because of changes in design standards.
Lanes are wider than they once were, Teague said, as are shoulders.
Department of Transportation ...
www.timesdaily.com, 29 June 2010 [cached]
Department of Transportation Preconstruction Engineer Allen Teague said plans involve adding an additional lane in each direction, with curbs, gutters and crossovers. Acceleration and deceleration lanes also are planned at the major intersections.
Median crossings that are not at major intersections will be removed, Teague said.
Allen Teague, a ...
www.timesdaily.com, 20 July 2011 [cached]
Allen Teague, a preconstruction engineer with the Alabama Department of Transportation, said the engineering part of the plan is on a fast track and is expected to be completed in the spring.
"What we're looking to do here is relieve some of the congestion," Teague said.
...
Teague said there is a better chance the three-lane
project, which carries an estimated cost of about $10 million, will be funded before the larger project, which is estimated to cost about $50 million.
The seven-lane widening project was halted in 2008 because of discrepancies between property owners and the state regarding appraised values of rights of way needed to complete the project.
Teague said negotiations to continue the acquisition of rights of way will continue.
"The other project is still a viable project," he said.
Allen Teague, a ...
www.timesdaily.com, 23 Jan 2011 [cached]
Allen Teague, a preconstruction engineer with the Shoals division of the Alabama Department of Transportation, said the estimated cost of the project is $265 million, which includes work that has been completed, contracts that have been awarded and estimates for future portions of the road project.
The number represents the cost of engineering work, rights of way, relocation of utilities and actual construction, Teague said.
...
Teague said the project is being completed in three phases. One phase is under way, while the two subsequent phases are in the design stage.
Teague said the subsequent projects are not scheduled until at least 2015.
...
The survey portion of the project between Dime and Alabama 195 has been completed and design work is under way, Teague said. The grade-and-drain portion is not scheduled to be sent out for bids until 2015.
Teague said surveying is under way on the southernmost segment of the project that runs from Alabama 195 to Delmar.
He said there are three sets of dual bridges along the route of the Spring Pine-to-Dime segment, two of which are under construction.
Other People with the name "Teague":
Other ZoomInfo Searches
Accelerate your business with the industry's most comprehensive profiles on business people and companies.
Find business contacts by city, industry and title. Our B2B directory has just-verified and in-depth profiles, plus the market's top tools for searching, targeting and tracking.
Atlanta | Boston | Chicago | Houston | Los Angeles | New York
Browse ZoomInfo's business people directory. Our professional profiles include verified contact information, biography, work history, affiliations and more.
Browse ZoomInfo's company directory. Our company profiles include corporate background information, detailed descriptions, and links to comprehensive employee profiles with verified contact information.
zirhbt201304